On an Austin build, I found a tendon resting on the vapor barrier, another running close to a plumbing pipe, and gaps beneath the wood forms. One opening, though, was there by design. The foundation plans showed which space the crew needed to leave open while there was still time to address the other findings.

Wood forms, red post-tension tendons, and black vapor barrier at an Austin slab before concrete placement
The Austin foundation before the pour. The forms, tendons, and black vapor barrier were still exposed.

What the plans showed near the tree

The structural drawings called for a reinforced cantilever on the side of the foundation next to a tree. A cantilever projects beyond its support, and in this case the plans called for open space underneath. That detail mattered when I checked where the steel sat and which openings around the forms needed attention.

There was a lot of rebar in that area. Looking through it, I saw one post-tension tendon resting against the plastic vapor barrier. The tendon needed support to hold it at its intended position while the concrete was placed. I flagged it for the post-tensioning crew and referenced the detail in the report.

Side-view diagram showing two support chairs holding a sheathed post-tension tendon above the vapor retarder
Support chairs help hold a tendon in position during the pour. Its intended position comes from the project drawings.
Dense reinforcing steel and a red-sheathed tendon at the Austin home’s tree-side cantilever
The tree-side reinforcement on this job. I documented the tendon support concern in this area.

Where the tendon passed close to a pipe

At another spot, a red-sheathed tendon passed close to a plumbing riser, the pipe that comes up through the slab. A post-tension tendon contains steel that’s pulled tight after the concrete has hardened. The routing and clearance can still be checked while the pipe and tendon are exposed.

I was concerned about possible interference or damage during stressing. My report asked the post-tensioning contractor to verify clearance and keep the intended tendon profile, with any needed routing change coordinated with the structural engineer.

Inspection photo with a blue arrow marking where a red-sheathed tendon passes close to a black-wrapped plumbing riser
The tendon passes close to the wrapped riser. This is the location I flagged for a clearance check.

Some openings needed closing. One was in the plans.

I found an opening in a perimeter form board and gaps under several other boards. Fresh concrete or paste could escape through those openings. I asked the formwork crew to close the gaps where needed and preserve the open space specified under the tree-side cantilever.

Two schematic sections compare an unintended opening below a wood form with the planned space below a projecting cantilever
The project drawings help tell a gap the crew should close from a space the foundation detail calls for.

A few other details were worth catching

  • Torn vapor barrier. The black sheet helps limit moisture from the ground. I found tears and punctures at several locations and recommended repairs using materials compatible with the installed sheet.
  • Loose reinforcement. Some rebar at a corner was unsecured, and tie wire was missing at multiple support chairs. Those pieces can shift during placement if they’re free to move.
  • Missing catheads. I flagged missing hardware, called catheads, at several tendon ends. I considered this a lower-priority item, and it was straightforward for the post-tensioning crew to verify which ends needed the hardware.
Tear in black under-slab vapor barrier exposing light-colored soil below
One of several openings in the vapor barrier documented before the pour.

Why I ask for the foundation plans

Most of the prep looked good to me. The drawings gave me a way to check the places that deserved a closer look, especially at the tree-side cantilever. While I was there, I also saw an engineer ask the crew to shift some rebar near a pipe closer to a form board. I recorded my own findings and their locations in my report for the builder. I didn’t verify whether those items were corrected before the pour.

A pre-pour inspection gives you a chance to ask about visible details like these before the concrete covers them. Bring the current foundation drawings and any revisions. If the builder makes a correction, ask for a photo that shows both the work and where it was done so you can match it to the report. See my guide to using engineered foundation plans for what to request.

What to ask before the pour

  1. When will the forms, reinforcement and plumbing be ready to inspect?
  2. Can you share the current foundation drawings and any details specific to this lot?
  3. Will there be time to review the findings and document any corrections before the pour?
Further reading from the Post-Tensioning Institute.